Newcastle + Lake Macquarie A kept record · entries dated and sourced

News · Planning pathway · Singleton

AGL asks the state to decide its $240m Liddell South works; Singleton’s mayor agreed in principle before councillors could vote

AGL wants the Planning Minister to declare the works that would turn 85 hectares beside the closed Liddell power station into an industrial precinct a State Significant Development, which takes the decision away from the local councils. The planning department gave Singleton Council 15 days to comment and refused to extend that by six days to reach the council’s 17 November meeting. So the mayor answered on the council’s behalf, supporting the state pathway in principle but not the project. Councillors see what was sent at that meeting, as an item for information only.

The Hunter Ledger · 14 November 2026 · 5 primary sources, read 14 November 2026

Planning pathway: a Hunter Ledger development graphic

The short answer. Item GM74/26 in the business paper for Singleton Council’s ordinary meeting on Tuesday 17 November reports a submission the mayor has already made. AGL Macquarie applied on 22 October for the Minister for Planning and Public Spaces to use the “call-in” power in section 4.36(3) of the Environmental Planning and Assessment Act. The department wrote to the council on 28 October asking for comments by 12 November. Council officers asked for an extension to 18 November, the day after the meeting, and the department declined on 30 OctoberA. The report says the mayor acted under section 226(d) of the Local Government Act, which lets a mayor exercise, in cases of necessity, the policy-making functions of the governing body of Council between Council meetings.

Exhibit A · from the source

Singleton Council business paper, 17 November 2026, item GM74/26, page 350: Council officers requested an extension until 18 November 2026 to allow the matter to be considered at Council's ordinary meeting on 17 November 2026. However, the Department declined this request on 30 October 2026.
Page 350 of the business paper for Singleton Council’s ordinary meeting of 17 November 2026, item GM74/26, read 14 November 2026. Outlined: the extension the council asked for, and the department’s refusal. Open the PDF at page 350 · Back to the story

What AGL wants to build

AGL owns about 10,000 hectares around the former Liddell Power Station, which closed in 2023, and the Bayswater Power Station, which its application says is scheduled to close by 2033. It is planning the whole holding as the Hunter Energy Hub. Liddell South is the next piece: an 85-hectare main precinct inside a project area of about 349.5 hectares that crosses the Muswellbrook and Singleton local government areas. The application seeks consent for the groundwork only, at an estimated capital investment value of about $240 million.

In the application, and not in it

What the Liddell South Precinct Enabling Works would cover, as AGL and the council’s report describe it.

Singleton Council business paper, 17 November 2026, item GM74/26 (pages 349 to 350) and Attachment 2, AGL’s call-in application of October 2026 (pages 357 to 358).

The site already has history with the state system. The demolition and remediation of the Liddell station itself, the Future Land Use and Enabling Works project, was approved as a State Significant Development in February 2025, covering around 143 hectares at more than $260 million. AGL’s application says it has built the 500 megawatt Liddell Battery on the site, and that the Hunter Energy Hub has been endorsed as a priority project by the NSW Investment Delivery Authority. Muswellbrook’s local environmental plan was amended in June 2025 to allow industries in the main precinct, the application says.

Why AGL wants the state to decide

The works do not qualify as State Significant Development on their own. The department’s letter to the council says the proposal does not trigger the criteria in State Environmental Planning Policy (Planning System) 2021, which is why AGL needs the Minister to call it in. AGL’s case runs through the six tests in the department’s call-in guideline: a site the Hunter Regional Plan 2041 names a regionally significant growth area, employment land in a region in transition, two council areas, and an assessment likely to involve Commonwealth environment law too, which an SSD declaration lets run through the bilateral process. Its summary of the alternative:

If the project is not called in as SSD, this project would require multiple separate Federal, State and local approvals which is an inefficient use of the planning system.

AGL Macquarie, Liddell South Precinct Enabling Works Project: request to declare the project to be State Significant Development, October 2026, page 358 of the council’s business paper

If the Minister agrees, the department assesses the project and a state consent authority decides it, rather than the councils. The report says Singleton would still be consulted on the assessment requirements, the environmental impact statement and the draft conditions. For how that track works and where its documents are published, see our guide to state significant development in the Hunter.

What the mayor sent, and what councillors will see

The mayor’s letter to the department is dated 2 November and attached to the report. It supports the declaration in principle because of the project’s cross-boundary location and the number of agencies involved, and fences that support off from the project itself:

Council's support relates only to the proposed planning assessment pathway and should not be interpreted as endorsement of the development itself

Singleton Council’s letter to the Department of Planning, Housing and Infrastructure, 2 November 2026, Attachment 3 to item GM74/26, page 430

The letter asks that any assessment deal with local and regional roads, water and wastewater, environmental values and the cumulative effect of the industry that would follow, that the council be consulted at every stage, and that infrastructure be paid for and maintained by the proponent or the relevant provider without creating unfunded obligations for Council. The report goes to councillors as an item for information, so there is no recommendation for them to vote on. It says its purpose is to provide transparency to Council regarding the circumstances requiring Mayoral consideration and what was communicated to the Department.

Fifteen days, and no council meeting inside them

Filled: happened. Open: the steps the department’s letter describes next.

  1. 22 October 2026AGL Macquarie applies for the Minister to call in the Liddell South works as State Significant Development
  2. 28 OctoberThe department writes to Singleton Council inviting comments by close of business on 12 November
  3. 30 OctoberThe department declines the council’s request for an extension to 18 November
  4. 2 NovemberThe mayor’s letter supports the declaration in principle, with qualifications
  5. 12 NovemberThe department’s deadline for comments
  6. 17 NovemberSingleton’s ordinary meeting receives the report for information
  7. No date givenThe department considers the request and sends it, with the council’s submission, to the Independent Planning Commission for advice
  8. No date givenThe Minister decides whether to call the project in
Singleton Council business paper, 17 November 2026, item GM74/26 (pages 349 to 351), the department’s letter of 28 October (Attachment 1, pages 353 to 354), AGL’s covering letter of 22 October (Attachment 2, page 355) and the mayor’s letter (Attachment 3, pages 430 to 431).

We will report the Independent Planning Commission’s advice and the Minister’s decision on the call-in when they are published.

Our view

This section is opinion, built on the facts above.

On the substance, the mayor’s answer is a sensible one, and the council’s officers reached the same view. A $240 million project across two council areas, sitting on land already covered by several existing consents and likely to need Commonwealth environmental approval, is the kind of thing the call-in power exists for. The qualifications are the right ones too, especially the insistence on no unfunded obligations: the roads, water and wastewater that serve a new industrial precinct are the costs most likely to land on a council later.

The process is the weak part. The department set a window of 15 days that held no Singleton council meeting, then refused to stretch it by six days so that one could be held. The decision it was consulting on does not end with the council’s comments either: the request still goes to the Independent Planning Commission for advice before the Minister decides. The result is that an elected council’s position on who should decide a project of about 349.5 hectares in its area was set by one person, under a power the Act frames around necessity, and the necessity was the department’s timetable. Singleton handled that openly, by putting the letter in front of councillors at the first meeting it could. The paper gives no reason for the refusal. A consultation window that spans one meeting cycle, or a published reason when it cannot, would let councils answer as councils.

Spotted an error in this story? Ask for a correction. Corrections are published, dated and left visible.