News · Port · Mayfield
A Mayfield berth is licensed to trial loading lead, zinc and copper concentrate. The air study behind it is not on the port’s website
On 12 December 2025 the NSW Environment Protection Authority varied the licence for the Port of Newcastle’s Mayfield No. 4 Berth to allow a 12-month trial of loading copper, lead or zinc concentrate onto ships, capped at 150,000 tonnes. The conditions are strict and the EPA wants a performance report at the end. But the air quality study it relied on, the trial’s own management plan and any metals monitoring results are not on the port’s website, and nothing published says whether the first load has arrived.
Metal concentrate is processed ore, the metal-rich product a mine sends on for smelting. The Port of Newcastle already ships plenty of it: its own trade report counts 530,684 revenue tonnes of mineral concentrate exports in 2025, up from 491,758 in 2024, bound for mainland China, Japan, South Korea, Malaysia and the Philippines (source 5). What is new is where. Mayfield No. 4 Berth is the multipurpose wharf off Selwyn Street, Mayfield North, built in the refurbishment of a former BHP wharf, and since December its licence has allowed a concentrate trial there (sources 1 and 3).
What the EPA licensed
The port applied on 12 September 2025. The EPA’s notice of variation, number 1653006, says
the application seeks to allow the handling and vessel loading of metal concentrates at the
premises
and was supported by two consultant documents of August 2025: an air quality impact
assessment for mineral concentrate export at the berth, and an operational environmental management plan
for mineral concentrate at the berth (source 1).
The licence now reads (source 2):
- A trial, not a standing approval. Loading is allowed
for a period of 12 months only
, and the 12 monthswill commence when the first load of metal concentrates are received at the premises
(condition L5.3). - Three metals. Copper, lead or zinc concentrates only (L5.4).
- A cap. No more than 150,000 tonnes over the trial (L5.5). For scale, that is a little over a quarter of the concentrate the whole port exported in 2025, though the trade report counts revenue tonnes and the licence counts tonnes.
- Sealed until it is in the ship. Container lids stay on until the containers are in the hold; containers are tipped only when completely within the hold, no more than 2 metres above the hull floor or cargo already loaded; the whole length of the ship is tarped to the berth to stop spillage into the water (O6.4 to O6.7).
- A dust stop. If excessive dust is seen during loading, all loading stops until it can
restart
without visible dust emissions
(O6.9). - Closed drains. Drains are cleaned before and after each loading; the drains at the front of the berth are closed beforehand; during loading and storage the front drains carry filter socks and the rear drains gross pollutant traps; and nothing may be discharged from three of the licensed discharge points while loading is under way (O6.10 to O6.14).
- Metals in the water tests. Copper, lead and zinc are added to the stormwater monitoring, sampled at the first discharge after a concentrate loading (M2.2, M2.3).
- A report at the end. Within three months of the trial finishing the port must give the EPA an environmental performance report covering the water results, the air monitoring results and what the trial taught (E2.2).
Why the EPA said yes
The notice gives the reasoning plainly. The EPA considered the application noting that the AQIA states
that modelling shows compliance for all pollutants under the proposed operational scenario
, and decided
to permit it on a trial basis subject to additional stringent conditions
(source 1). It records that
the variation will not authorise a significant increase in environmental impact
. The licence explains
the purpose of the report at the end: the approach will enable data-based decision making when assessing
the long-term viability of the proposal
(source 2, condition E2.1).
What the public record does not show
We looked in the places a reader would: the EPA’s public register, the port’s policies and compliance page, which lists the berth’s licence, plans and approvals, the port’s environmental monitoring page, and the port website’s own search and page lists. As at 28 October 2026:
- The air quality study is not there. The modelling the EPA relied on is named in the
notice, but neither it nor the concentrate management plan is among the documents on the port’s
compliance page, and the website’s search for
concentrate
finds only a 2023 trade release (source 4). - The published operating plan does not deal with the trial. The berth’s operational
environmental management plan, version 7 of 27 May 2026, approved by the Department of Planning, Housing
and Infrastructure on 28 August 2026, lists the berth’s expected cargoes for 2025 to 2027 with no
concentrate line (pages 6 and 8). Its air quality section describes a monitoring station that
measures PM10 and TSP
, two measures of airborne dust, and says thatGiven that the site is completely sealed, no air quality issues are anticipated for the site
(page 30). The licence notice is appended to the plan, but the trial’s air monitoring programme is in section 5.3.2 of the separate concentrate plan, which is the document that is not published (source 3). - No metals results yet. The berth’s stormwater reports on the port’s monitoring page run to November 2025, before the variation (source 4).
- No start date. Because the 12 months run from the first load, the trial could have started at any time since December, or not at all. No document we found says which.
- No promise to publish the report. The licence requires the performance report to go to the EPA. It does not say the report will be made public.
The plan does give the setting: the berth sits in an industrial port area, with the Mayfield East
residential area located approximately 1.4km to the southwest across Industrial Drive
(source 3, page 2).
Our view
A capped, time-limited trial with sealed containers, in-hold tipping, a dust stop and a report at the end is a sensible way to test a new cargo on an old steelworks wharf, and the EPA’s conditions read as though someone thought hard about how lead-bearing dust escapes. The weakness is not the conditions. It is that the trial’s evidence runs entirely between the port and the regulator. The only published operating plan for the berth tells a reader no air quality issues are anticipated, while the document that actually governs air monitoring for concentrate sits unpublished.
A trial whose purpose, in the EPA’s words, is data-based decision making should put its data where the people downwind can read it. The port should publish the air quality assessment and the concentrate management plan now, say when the first load arrived, and post the copper, lead and zinc stormwater results alongside the dust results it already publishes. The EPA should publish the performance report before it decides whether the trial becomes permanent.
What to watch
- Stormwater reports for the berth carrying copper, lead and zinc results, which would show that loading has happened.
- Any further variation to the licence: making the trial permanent, extending it or ending it would each need one.
- The performance report, due within three months of the trial’s end.
Sources
- NSW Environment Protection Authority, notice of variation of licence no. 13181, notice number 1653006, issued 12 December 2025 under section 58(5) of the Protection of the Environment Operations Act 1997 (PDF, 25 pages, read 28 October 2026). Find it on the EPA’s POEO public register by choosing Notices and searching notice number 1653006; the register does not give the notice a fixed address. Source for the application date, the quoted purpose, the two supporting documents, the EPA’s reasoning and the list of varied conditions.
- NSW Environment Protection Authority, Environment Protection Licence 13181, licence version date 12 August 2026 (as published by the Port of Newcastle, PDF, 27 pages, read 28 October 2026): conditions L5.3 to L5.5 (page 12), O6.4 to O6.14 (page 14), M2.2 and M2.3 (pages 15 and 16), and special condition E2 (pages 20 and 21). The trial conditions added in December 2025 remain in this version.
- Port of Newcastle, Mayfield No. 4 Berth (DA 293-08-00) Operational Environmental Management Plan, version 7, 27 May 2026 (PDF, 23.8 MB, read 28 October 2026): the approval date in its document control table, the berth’s setting (page 2, PDF page 10), the potential cargo list and cargo table (pages 6 and 8, PDF pages 14 and 16), and the air quality section (page 30, PDF page 38). Page numbers are the plan’s own.
- Port of Newcastle, Policies and compliance and Environmental protection monitoring (both read 28 October 2026): the documents listed for the berth, and the stormwater reports, the latest of which is for November 2025. The website’s search for
concentrate
and its post and page sitemaps were also checked on 28 October 2026. - Port of Newcastle, 2025 Annual Trade Report (PDF, read 28 October 2026): mineral concentrate exports of 530,684 revenue tonnes in 2025 and 491,758 in 2024 (page 3), and their destinations (page 7).
Methodology. The notice was downloaded from the EPA register and the licence, plan and trade report from the port’s website, and all four were read in full rather than through a summary. Every statement that a document is not public is limited to the places named above, checked on 28 October 2026; a document published somewhere else would not have been found. We have not asked the port or the EPA whether the trial has begun, so this story does not say either way. The comparison of the 150,000-tonne cap with the 2025 export figure is ours and is approximate, because the two documents count different kinds of tonne. No individual is named: the notice’s addressee and signatory are left out as they add nothing a reader needs.
Spotted an error in this story? Tell us and we will correct it and say so.