News · Planning · New Lambton
Newcastle endorsed a landslide risk map over 37 New Lambton lots. It would end complying development there
The map reaches past the 16 residential properties evacuated after the May 2025 slip, because the council’s geotechnical report found a broader area that may be susceptible to land movement. An interim council policy has applied since 8 September: development applications there should come with a site-specific geotechnical report, and planning certificates will carry advice that the land has the potential to be impacted by landslide. The change to the local environmental plan goes next to the state for a gateway determination; the council’s timeline anticipates the plan being made in July 2027.
The short answer. If you own one of the 37 lots on Russell Road, Baker Street,
Victoria Street, Portland Place or Curzon Road that City of Newcastle’s planning proposal lists
around the New Lambton landslide, two things apply. One is already in force: since 8 September 2026
an interim council policy says a development application there should be supported by a
site-specific geotechnical report prepared by a suitably qualified geotechnical engineer
, and a
planning certificate for the land will carry advice that the land has the potential to be
impacted by landslide
. The other is proposed: a new clause and map in the Newcastle Local
Environmental Plan 2012 which, the proposal says, means that complying development cannot be
carried out on the Applicable Land
. Your zoning does not change. The council says it has
contacted the owners of the properties that may be affected.
Why the map is wider than the slip
The landslide began on 23 May 2025, in a severe weather event that led to a natural disaster
declaration across the Hunter and Mid North Coast. The council’s report says 16 residential
properties and 44 residents were evacuated, and a declared Danger Area still keeps residents out of
their homes (report page 4). The planning proposal says that since the first event the landslide
has continued to move and grow in extent
(page 3).
The council commissioned a detailed geotechnical investigation from RCA Australia, acknowledged by
council on 24 February 2026. According to the planning proposal, it found the slip was caused by
heavy rainfall and adverse groundwater, and No connection was found between the presence of mine
workings beneath the Applicable Land to the landslide.
(page 12). It split the ground into two
zones: Zone A, with only minor movement, and Zone B, with a deep head scarp, tension cracks and
damage to buildings. Because the report concluded the slope cannot be fixed lot by lot, the proposal
treats both zones as a single landslide-prone area
(page 4). The council report puts it
plainly: the map extends beyond the properties directly affected by the May 2025 landslide
because the RCA Report identified a broader area with geotechnical conditions that may be
susceptible to land movement.
(pages 1 to 2).
The 37 lots on the proposed Landslide Risk Map, by street
One square per lot, as listed in the planning proposal’s schedule of the land it applies to. Part of the road reserve in Russell Road, Baker Street and Victoria Street is also included.
- Russell Road 12
- Victoria Street 9
- Curzon Road 6
- Portland Place 6
- Baker Street 4
Two zones, one rule: the proposal applies the same controls to Zone A land that has moved only a little
as to Zone B land with significant instability. The proposal quotes the RCA report’s own line that
all areas and properties in the affected area will require specific geotechnical advice
(page
12). It also leaves the door open beyond New Lambton: Further areas outside of the mapped
Applicable Land and scope of the Planning Proposal may be investigated in the future to determine
landslide risk.
(page 15).
What applies now, and what would change
Two documents do two jobs. The interim policy, approved by the chief executive and in force from 8
September 2026, tells applicants what the council will generally ask for and weigh. The report says
it does not replace statutory planning instruments and does not prohibit development
(page
2). The planning proposal would put the rule into the local environmental plan itself, which it says
Creates a legally binding requirement for development stakeholders to ensure landslide risk is
appropriately considered
(page 13).
The interim policy against the proposed plan clause
Development applications
NowShould come with a site-specific geotechnical report that shows the RCA findings were considered. Consent is unlikely to be supported
where the land is not suitable for individual lot remediation
(policy pages 2 to 3)
ProposedProposals must show that site layout, earthworks, drainage, stormwater, wastewater and construction methods are designed with regard to landslide risk, and the consent authority must consider it (proposal page 10), putting an onus on owners and applicants to prove
a development is appropriate (page 12)
Complying development
NowNot covered. The policy’s definition of a development application does not include an application for a complying development certificate
(policy page 4)
ProposedRuled out. complying development cannot be carried out on the Applicable Land
(proposal page 10)
Zoning and building limits
NowR2 Low Density Residential, 400 square metre minimum lot size, 8.5 metre height limit (proposal page 7)
ProposedUnchanged. No changes to land use zones or the development standards in Part 4 of the NLEP 2012 are proposed.
(proposal page 10)
How long it lasts
NowUntil 30 April 2030, or until the plan clause commences (policy page 7)
ProposedPart of the local environmental plan once made
The complying development row is the reason the council gives for the change. Its report says
that until the NLEP 2012 is amended, there is a risk that development may proceed without a
development application or without mandatory consideration of the site-specific landslide risks
identified by the RCA Report.
(page 3). The policy also says the mapped area may be updated
from time to time to reflect new information, including post rainfall movement of land
(page
2).
Where the recovery stands
The plan change is about future building on the slope, not about the 16 evacuated households. On
their recovery, the council’s report says council resolved in July 2025 to seek an NSW Government Act of
Grace payment for affected ratepayers, and that The Minister for Recovery refused this request in a
letter dated 23 December 2025.
(page 4). In February 2026 council resolved to ask the NSW
Reconstruction Authority to urgently consider state-funded hardship and rental assistance for displaced residents.
On 22 May 2026 the council said it was working with the Reconstruction Authority to finalise a
funding package to enable the demolition of properties affected by the New Lambton landslip and
compensate residents for the loss of their land.
Its chief executive, Jeremy Bath, said residents
would move to a 12-month relocation package funded by the NSW Government, that the funding needed
state and federal contributions which are not committed yet
, and that demolition was not
likely to start until early 2027. The council’s latest update, on 15 September, says new
geotechnical investigations began that month to plan long-term stabilisation, that monitoring
has not recorded any significant movement or trends that indicate the size of the landslip zone
has increased
, and that the timing of an approved funding program is still to be
determined
.
We continue to work with the RA on behalf of the residents to identify a long-term solution that stabilises the ground. Sadly, these works won’t permit future development on the site.
The council has also resolved to keep giving affected landowners a rates rebate until they sell or can move back in, as it did in 2025-26, according to its 5 June update. It said in April it expected about $2.6 million in landslip costs in the 2025-26 financial year, money not in its adopted budget.
What happens next
Council carried the recommendation on 22 September without a recorded division; the unconfirmed
minutes record it as Carried
(pages 10 to 11). It endorsed sending the proposal to the state planning
department for a gateway determination, requesting the role of planning proposal authority; the
proposal’s timeline has the council exercising the local plan-making functions. The proposal sets public exhibition at 28 days or as the gateway directs
(page 31), and the report says exhibition will include written notification to property owners,
and adjoining and nearby property owners
(page 4). Owners in and outside the affected area can
make a submission
, it says.
From the slip to a plan clause
Filled: happened. Open: the dates the council’s own timeline anticipates, as at 8 October 2026.
- 23 May 2025Landslide at New Lambton; 16 residential properties and 44 residents evacuated
- 23 December 2025Minister for Recovery refuses the council’s Act of Grace request, the council report says
- 24 February 2026Council acknowledges the RCA geotechnical report as the technical basis for recovery planning
- 22 May 2026Council says it is working with the Reconstruction Authority on a funding package for demolition and compensation
- 8 September 2026Interim Landslide Risk Assessment Policy commences
- 22 September 2026Council endorses the planning proposal, carried
- October 2026, anticipatedGateway determination from the state planning department
- After the gatewayPublic exhibition, 28 days or as the gateway directs, with letters to owners and neighbours
- April 2027, anticipatedReport back to council for adoption
- July 2027, anticipatedPlan made; notified in August 2027
Our view
This section is opinion, built on the facts above.
Mapping the whole slope rather than the 16 broken properties is the right call, and the council has the evidence for it: its own geotechnical report says the slope can only be fixed as one piece, so a renovation on a Zone A lot is a question about Zone B. What the documents also show is a gap. By the council’s own account, until the plan is amended there is a risk that development may proceed without a development application, and its timeline anticipates closing that in July 2027, more than two years after the slip. A gateway that comes back quickly would shorten that.
For owners at the edge of the map, the planning certificate advice is the part with consequences today, and it arrived by an operational policy approved by the chief executive, while the plan change will go on public exhibition. The fair test of the exhibition will be whether those owners get a real hearing on where the line falls. We will add the gateway determination and the exhibition dates to this story when they are published.
Spotted an error in this story? Ask for a correction. Corrections are published, dated and left visible.